The Challenge

  • Risk assessment
  • Identify ground deformation
  • Effects on adjacent structures

The I-93 South Station project involved the construction of a passageway for the northbound barrel of the Central Artery Tunnel project beneath the Massachusetts Bay Transportation Authority’s (MBTA) South Station, which serves the Red Line subway. The work also involved a 110-ft deep excavation immediately adjacent to Amtrak’s South Station terminus. The contract method consisted of the construction of structural slurry walls down the outer limits of the work perpendicular and beneath the MBTA station. Thirteen tunnels were then constructed beneath the station roughly parallel, one at a time.

A large beam would be placed in each tunnel and rested on the structural slurry walls. This would create an underground bridge to support the Red Line Station while soil and rock was excavated below and the new highway tunnel constructed.

The Solution

The construction of the I-90 interchange for the Central Artery Tunnel in Boston involved deep excavations, cut and cover tunneling, pipe-jacking through frozen ground, and soil mix techniques for ground improvement, all taking place adjacent to and under seven (7) Massachusetts Bay Transportation Authority (MBTA) and Amtrak tracks leading to Boston’s South Station.

Geocomp was responsible for all of the geotechnical monitoring work which included installing piezometers, observation wells, extensometers, inclinometers, and support-of-excavation walls, as well as structural monitoring including tilt, crack gages, and measuring horizontal column deformation in nearby structures.

 A risk assessment approach was also presented, identifying the amount of ground deformation that might occur and how it might impact the MBTA station. Geocomp staff performed a comprehensive three dimensional finite element analysis of both methods of construction and compared the predicted deformations. The results showed that the tunneling method would produce less displacement of the MBTA station and also create less risk for the contractor and the owner.

Services Provided

3D Finite Element Analysis

Risk assessment and three-dimensional finite element analysis to evaluate deformation

Geotechnical Monitoring

Installation of the geotechnical monitoring: piezometers, observation wells, extensometers, and inclinometers

Structural Monitoring

Measuring for tilt, cracks, and horizontal column deformation in nearby structures

Related Projects

GEOPROJECT_Betsy's Cove

Betsy’s Cove

Value Delivered:

Lowered project construction costs with design
improvement recommendations for stability
GEOPROJECT_Katrina Litigation

Katrina Litigation

Value Delivered:

Comprehensive data and expert testimony on failure cause
Scour from floodwall overtopping caused both failures
GEOPROJECT_TVA Risk

Tennessee Valley Authority (TVA)

Value Delivered:

Using risk monitoring to help manage major risks for
public safety
Automatically notify required staff on issues and problem
solve quickly and efficiently

Ready to Speak
with our
Experts?