The Challenge

  • Massport manages Boston’s Logan International Airport
  • Over $4.4 billion invested in runway, roadway, and terminal construction
  • Taxiway M, part of safety improvements, aimed to reduce runway crossings and ground delays

The Massachusetts Port Authority (Massport) operates Boston’s Logan International Airport. In the last decade, Massport and its airline partners have invested more than $4.4 billion to build a new runway, roadways, and terminals. The construction of Taxiway M was commissioned in 2008 as one of several projects to help with safety at the airport after a series of incursions occurred. The taxiway was being built to decrease the number of runways that planes must cross and to reduce ground delays. Logan airport is built on filled land in Boston Harbor. Runways and taxiways are approximately 15 feet above sea level. Ground water levels in the filled soil are affected by the daily tidal fluctuation.

TBD

The Solution

Construction of Taxiway M required the contractor to excavate approximately 4 to 5 feet of the filled material to a depth where the underlying soil was saturated. Subsequent to construction of one section of the taxiway, settlement was observed which required reworking the constructed area. To avoid this condition in future construction, the contractor turned to Geocomp to devise a method and system to monitor potential settlement as construction progressed. Geocomp’s challenge was to design a liquid level settlement system to measure the differential settlement between two points.

The system was comprised of three vibrating wire liquid level settlement sensors, installed at the bottom of the excavation, and perpendicular to the taxiway centerline. As backfilling and compaction took place, the sensors measured the changes in pressure. The sensor data was recorded automatically by a Geocomp data logger and transmitted in real-time to Geocomp’s web-based monitoring system, iSiteCentral®.

Services Provided

Settlement Solutions

Liquid level settlement system design

Implementing Control

Installation and management

Settlement Monitoring

Real-time data to detect and compensate for settlement

Related Projects

GEOPROJECT_Atlanta International Airport

Atlanta International Airport

Value Delivered:

Reduced risk by monitoring unexpected performance
during construction
Enabled proactive and cost-effective approach to
managing risk by implementing a data management system
that showcases early warnings of unacceptable performance
GEOPROJECT_Dulles International Airport

Dulles International Airport

Value Delivered:

Real-time performance monitoring provided essential
data for assessing deformation/movement during construction
Automated data logging allowed for multiple daily
readings in critical or restricted construction areas
Seamless integration of GeoMoS and iSiteCentral®
GEOPROJECT_Honolulu Airport

Honolulu Airport

Value Delivered:

University of Hawaii used the data for student research
and continues to do so for the new few years

Ready to Speak
with our
Experts